元に戻るhomenext

Large-sized Meteorological Environment Testing Chamber

In order to create an even better Environment Chamber, you can be better understood by looking at the procedure for carrying out the installation.

1.

3.

5.

7.

9.

11.

1. Determining the installation location The location must be determined by considering the size of the installation and the bringing-in of machinery parts. In order to bring in large-sized machine parts, an adequate frontage space is required. If the installation is not on the ground floor, the use of a crane may be required. The same amount of preparation space as installation space is required.

2. 3. Inking and skid assembly While using a spirit level to carry out precise leveling, by matching the inking lines, the skids are constructed that become the foundations for the panels. The main chamber, surroundings, and ceiling height should have approximately 500 mm margin to allow builders' access.

4. 5. Laying the floor panels The outer covering is vinyl chloride coated steel plate, and the interior uses SUS 304. Because the foaming of the urethane resin gives a 1 ton/m² load, the surface load will be able to withstand a 1 ton load. The laying of the light-weight high rigidity heat resistant panels is than completed. Using silicone caulking between the panels, a high degree of air tightness and heat resistance is ensured.

6. 7. Mounting the ceiling panels Different installation methods will be used for especially large- sized testing chambers. The safest method is used, which may include suspension from channels, suspension from the installation location building joists, supporting by using construction materials, etc.

8. Conditioning machine mounting When constructing the conditioning machine that consists of the boiler unit, cooling cooling coil unit, heater unit and agitating fan, these items should be fixed to the main unit with attaching fixture called fasteners, because they are fairly heavy compared to the panels.

9. Door mounting Depending on the dimensions of the object to be put in the chamber, either a single door (W 700×H1800) or a duple door (W1400×H2000) should be selected.

10. Finishing After completion of the assembly of all panels, silicone caulking is carried out to complete work on the outside walls of the main unit. . By carrying out instrumentation mounting electrical wiring work for the sensors and lighting, etc. and in stalling the refrigerator and cooling wiring and water piping, the work is completed.

2.

4.

6.

8.

10.

DS wet -40ºC spec. DS dry -40ºC spec.

DS wet -30ºC spec. DS dry -30ºC spec.

DS wet -20ºC spec. DS dry -20ºC spec.

DS wet -10ºC spec. DS dry -10ºC spec.

DS wet RT spec. DS dry RT spec.

元に戻るhomenext

E-mail: info@kato-inc.com